兰州地铁1号线盾构下穿黄河强透水地层施工安全性研究  被引量:11

Study on Construction Safety in Case of Lanzhou Metro Line No.1 Shield Tunnel Passing Through Strong Permeable Stratum Under the Yellow River

在线阅读下载全文

作  者:邓如勇 汪辉武 戴兵[2] 方勇[1] DENG Ruyong WANG Huiwu Dai Bing FANG Yong(Key Laboratory of Transportation Tunnel Engineering, Ministry of Education, Southwest Jiaotong University, Chengdu Sichuan 610031, China China Railway 16th Group Co., Ltd., Beijing 100018, China)

机构地区:[1]西南交通大学交通隧道工程教育部重点实验室,四川成都610031 [2]中铁十六局集团有限公司,北京100018

出  处:《铁道建筑》2016年第9期57-61,共5页Railway Engineering

基  金:国家自然科学基金(51278422;51578460);国家科技支撑计划(2012BAG05B03);四川省青年科技基金(2012JQ0021)

摘  要:以兰州地铁1号线迎门滩—马滩区间盾构下穿黄河段地铁隧道工程为背景,采用FLAC3D软件对下穿黄河强透水砂卵石地层施工过程进行了数值模拟,对潜在的施工风险进行了分析。结果表明:盾构下穿黄河会造成河堤不均匀沉降,沉降的强影响区为距两隧道中心线约15 m宽度范围内;掌子面支护压力越大,拱顶沉降越小,但支护压力增加会造成临近线路管片应力和位移增大,故应根据实际情况调整掌子面支护压力;拱顶注浆压力为0.2 MPa时管片上浮量最小;掌子面附近土体位移随掌子面支护压力的增大而减小,本工程带压换刀时掌子面支护压力宜控制在0.5 MPa。Taking the interval shield tunnel between Yingmentan station and Matan station of Lanzhou Metro Line No.1 passing through the Yellow River subway tunnel project as background,the FLAC3 D software was used to simulate the construction process of shield tunnel passing through the strong permeable sandy gravel stratum under Yellow River and the potential construction risks were analyzed.Research results show that the shield passing through the Yellow River will cause the uneven settlement of the embankment,the strong impact zone of which is about 15 m width range away from the center line of two tunnel,the vault settlement will decrease with the tunnel face support pressure increasing and the increase of support pressure may lead to the stress and displacement increasing of the adjacent line segment,which means the tunnel face support pressure should be adjusted based on the actual situation,the upward moving of the line segment is minimum when the vault grouting pressure is 0.2 MPa,the soil displacement near the tunnel face decreases with the support pressure increasing,and the tunnel face support pressure should be about 0.5 MPa when the cutters were replaced with the air pressure.

关 键 词:兰州地铁 强透水地层 盾构施工 施工安全性 

分 类 号:U455.43[建筑科学—桥梁与隧道工程]

 