拉洛工程导流洞全断面衬砌施工技术与质量控制  

Full-section lining of diversion tunnel and quality control for Laluo Project

在线阅读下载全文

作  者:陈佳栋[1] 郭俊波[1] 肖梦奇[1] 

机构地区:[1]中国人民武装警察部队水电第三总队,成都610036

出  处:《中国水利》2016年第20期68-70,共3页China Water Resources

摘  要:导流洞衬砌混凝土施工直接影响拉洛水利枢纽截流节点工期,洞衬有效施工时间为100天,工期紧,施工强度大,为满足工期要求,采用2台12 m长全断面针梁式钢模台车进行浇筑施工。着重介绍全断面针梁式钢模台车施工工艺及其质量控制措施,对类似工程施工具有一定的借鉴意义。Concrete lining of diversion tunnel has a direct influence on the time of damming of Laluo Project.Therefore, two 12-meters-long steel-mould stair vehicles of needle bridges were employed for pouring construction, so as to meet the time limit of Laluo Project that has a tight schedule for lining of 100 days and high construction intensity. The paper focuses on introduction of construction technique and quality control measures that shall be useful for conference of similar projects.

关 键 词:拉洛水利枢纽 导流洞 混凝土衬砌 质量控制 

分 类 号:TV554[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象