立井穿过油页岩层快速施工技术  

Rapid Construction Technology of Mine Shaft Passed through Oil Shale Stratum

在线阅读下载全文

作  者:李刚[1] 王雨寒[1] 

机构地区:[1]中煤第一建设有限公司第四十九工程处,河北邯郸056003

出  处:《建井技术》2016年第5期1-3,24,共4页Mine Construction Technology

摘  要:依兰第三煤矿主立井深度708m,采用立井综合机械化配套作业线施工,钻爆法掘进。油页岩层处于490~614.8m深位置,厚度124.8m,可能赋存有毒、有害气体。采用先探后掘、短段掘砌的方式,安全快速地通过了该岩层,最高月成井101m,整个井筒施工工期比合同工期提前了32d。A mine main shaft of Yilan No. 3 Mine was 708 m in depth. A fully mechanized matched op- eration line was applied to the construction of the mine shaft and a drilling and blasting method was applied to the mine shaft sinking. A oil shale stratum was at a depth location of 490-614.8 m and the thickness of the stratum was 124.8 m. And there were toxic and harmful gas existed in the stratum possibly. The construction method with an exploration first and sinking second and a short sectional sinking and lining was applied. The mine shafts were safely and rapidly passed through the rock stra- ta. The max month shaft completed was 101 m and the total construction period of the mine shafts was 32 days earlier than the contract period.

关 键 词:立井 油页岩层 快速施工 钻爆法 先探后掘 

分 类 号:TD262.65[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象