FPSO发电机组模块吊装方案  被引量:1

Lifting of FPSO's Generator Set Module

在线阅读下载全文

作  者:钟伟怀 

机构地区:[1]中船澄西船舶(广州)有限公司,广州511462

出  处:《广东造船》2016年第6期58-60,共3页Guangdong shipbuilding

摘  要:发电机组是FPSO最重要的模块之一,发电机组模块由钢结构及设备构成,重量约500 t,需通过专用吊梁才能吊装。船东对模块安装精度及吊装安全措施要求严格,模块支座有多根支撑,且FPSO型深很大,水面以上高度达到23 m,模块底部距离吊钩68 m,安装支座高度约5 m,吊装间隙约1 m,总体安装高度达到97 m,对模块吊放到位及浮吊的要求极高。The generator set module is one of the most important module of FPSO, it is composed of steel structural members and equipment with total weight is about 500 tons and will be lifted by a special lifting beam. The ship owner has stringent requirements for the installation accuracy and safety control of the module, there are much supports for the module foundation, FPSO's mould depth is large, the FPSO's side shell is about 23 m above water, the space between the bottom of the module and the hook of the crane is about 68 m, the foundation height is about 5 m and the lifting space is only lm and the total lifting height reaches 97 m, therefore the lifting work of the module is very hard.

关 键 词:FPSO 模块 吊装 

分 类 号:U671[交通运输工程—船舶及航道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象