福清核电P320控制系统调试方案分析  

The Analysis of P320 Control System Debugging Scheme of Fuqing Nuclear Power Plant

在线阅读下载全文

作  者:蔡红伟 肖付伟 李德银 张立蕊 

机构地区:[1]福建福清核电有限公司,福建福清350300 [2]中广核研究院有限公司北京分公司,北京100086

出  处:《仪器仪表用户》2017年第3期77-79,45,共4页Instrumentation

摘  要:汽轮机控制系统是核电站的重要控制系统之一。核电机组控制系统调试过程中会遇到一些问题,如果不能得到及时的解决,会对核电的安全运行产生重大的影响。福清1号机组的汽轮机控制系统采用ALSTOM P320 V2+控制平台。因此,这里针对福清核电1号机组P320控制系统在调试过程中遇到的问题及相应的解决方案进行分析和总结,对今后的汽轮机控制系统的正常运行有着重要意义。The turbine control system is one of the important control systems of the plant. Control systems in nuclear power units may encounter some problems in the process of debugging. It will have a very bad impact on the nuclear power if these problems cannot be solved in time. ALSTOM P320 V2 + platform is adopted in the turbine control system of Fuqing unit 1. Therefore, we analyze the problems in the debugging process of P320 control system of Fuqing unit 1 and make a conclusion on the solving methods, whieh is meaningful for the future operation on the turbine control systems in the nuclear power plant.

关 键 词:汽轮机控制系统 福清1号机组 核电站 分析总结 

分 类 号:TP216.1[自动化与计算机技术—检测技术与自动化装置]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象