500kV架空导线高空移位临档接续修复工艺  被引量:3

Technology of Connection and Repair at Adjacent Span with High Altitude Displacement on 500 kV Overhead Conductors

在线阅读下载全文

作  者:李博亚 朱迪锋 刘红鑫[1] 汪丽波[1] 

机构地区:[1]国网浙江省电力公司检修分公司,杭州311232

出  处:《浙江电力》2017年第3期34-37,共4页Zhejiang Electric Power

摘  要:某500 kV架空输电线路导线严重受损,且导线受损点所在档距内存在接续管,给修复工作带来困难。为满足《110~750 kV架空输电线路施工及验收规范》要求,采用导线高空移位临档接续的方法进行修复,并详细介绍了施工工艺流程。与直接更换导线工作相比,应用该方法能最大限度降低修复工作量和工作难度,有效提高线路检修工作效率。A 500 kV overhead transmission line was severely damaged, and there was a connecting tube in the span in which the damage point exists, bringing difficulty to wire repair. In order to meet the requirements of 110~750 kV Overhead Transmission Line Construction and Acceptance Norms, the wire is repaired at adjacent span with high altitude displacement, and construction technology process is detailed. In contrast to direct replacement of wire, this method can greatly reduce work load and difficulty, and can improve line maintenance efficiency.

关 键 词:输电线路 导线 修复 临档接续 

分 类 号:TM755[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象