察哈素煤矿大采高工作面巷道布置优化设计  被引量:1

Optimization Design of Roadway Layout in Chahasu Coal Mine Fully Mechanized Working Face

在线阅读下载全文

作  者:王志强[1] 王建明[1] 马奇飞 司永达 徐杰[1] 张佩璇[1] 刘小田[1] 

机构地区:[1]中国矿业大学(北京)资源与安全工程学院,北京100083

出  处:《煤矿安全》2017年第3期144-146,151,共4页Safety in Coal Mines

基  金:国家自然科学基金资助项目(51404270);中央高校基本科研业务费专项资金资助项目(2011QZ06)

摘  要:针对察哈素煤矿3#煤层赋存条件及工作面原有巷道布置特点,通过对顶板岩层取芯分析、多点位移计观测和现场矿压实测分析,得出巷道顶板在0~3 m范围内发生破坏及下位岩层之间发生层间错动。采用错层位采煤法解决了以上现象带来巷道支护困难的问题。对优化方案进行了工作面设计并通过计算得出可以提高回采率2.7%,充分证明了错层位采煤法的实用和可靠性。According to the occurrence conditions of 3^# coal seam and layout characteristics of original roadway at working face in Chahasu Coal Mine,through the analysis of roof rock core analysis,multi-point displacement meter observation and field mine pressure measurement analysis,we obtain that the roof failure of roadway and the occurrence of intercalated dislocation between the lower rock strata is within the range of 0 to 3 m.To solve the above problems,the phenomenon of roadway support difficulty is solved by stagger arrangement coal mining method.The optimization scheme is designed and the working face is calculated,which can improve the recovery rate of 2.7%.It fully proves the practicability and reliability of the stagger arrangement coal mining method.

关 键 词:顶板离层 错层位 煤柱 巷道破坏 三角煤 

分 类 号:TD822.2[矿业工程—煤矿开采]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象