武钢1号高炉中修开炉操作实践  

Operation practice of blow-in after intermediate overhaul of No.1 BF in WISCO

在线阅读下载全文

作  者:唐少波[1] 仉翼鹏[1] 黄珂[1] 严琳波[1] 

机构地区:[1]武钢炼铁厂,湖北武汉430083

出  处:《武钢技术》2017年第2期11-15,共5页Wisco Technology

摘  要:对武钢1号高炉2016年3月28日中修开炉过程进行了总结,介绍了开炉配料与装料、送风操作、焦炭负荷、装料制度等工艺参数的调剂过程。高炉开炉历时43h即恢复至正常水平,整个开炉进程顺利、快速、安全,为武钢今后的开炉操作积累了实践经验。The process of blow-in after intermediate overhaul of No. 1 blast furnace in WISCO on March 28, 2016 was summarized. Adjusting processes of technical parameters such as batching and charging, air delivery operation, burden ratio, charging system of the blow-in operation were introduced. It merely took 43 h for blow-in before returning to the normal level of blast furnace. The smooth, quick and safe blow-in process has accumulated some experiences for the future blow-in operation in WISCO.

关 键 词:高炉 开炉 送风 装料制度 

分 类 号:TF542.5[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象