孤岛综放面沿空掘巷窄煤柱合理宽度确定  被引量:4

Reasonable Width of Narrow Coal Pillar on Gob-side Entry at Island Fully Mechanized Caving Face

在线阅读下载全文

作  者:臧传伟[1] 孙景涛[1] ZANG Chuan-wei SUN Jing-tao(College of Mining and Safety Egineering, Shangdong University of Science and Technology, Qingdao266590, Chin)

机构地区:[1]山东科技大学矿业与安全工程学院,山东青岛266590

出  处:《煤炭技术》2017年第5期26-27,共2页Coal Technology

摘  要:为解决孤岛综放工作面沿空掘巷小煤柱宽度确定的难题,以鲍店煤矿103上05(2)孤岛工作面地质情况为工程背景,首先通过力学模型对孤岛综放工作面的沿空掘巷煤柱宽度进行分析计算,确定煤柱宽度应大于2.22 m。然后运用数值模拟研究了不同煤柱宽度下的巷道变形规律,最终确定煤柱宽度为4 m。In order to solve the problem of determining the width of narrow coal pillar on gob-side entry at island fully mechanized caving face,the geological situation of Baodian coal mine 103~05 ~ face was regarded as the engineering background, firstly, the coal pillar width of gob-side entry driving in fully mechanized caving face is calculated and analyzed by mechanical model,the width of the coal pillar was determined to be 2.22 m at least,secondly,the deformation laws of surrounding rock deformation with different widths of narrow coal pillar were researched by using numerical analysis; the reasonable width of narrow coal pillar in Baodian coal mine can be determined about 4 m.

关 键 词:孤岛工作面 沿空掘巷 煤柱宽度 

分 类 号:TD823.5[矿业工程—煤矿开采]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象