浅谈清远抽水蓄能电站引水隧洞V类围岩洞段的灌浆处理  

Grouting Treatment for Headrace Tunnel Section in Class V Surrounding Rock at Qingyuan Pumped Storage Power Station

在线阅读下载全文

作  者:寇文博 

机构地区:[1]中国水利水电第五工程局有限公司,四川成都610066

出  处:《四川水力发电》2017年第3期75-78,共4页Sichuan Hydropower

摘  要:广东清远抽水蓄能电站引水隧洞中平洞V类围岩洞段地质情况极其复杂,钻孔过程中易发生涌沙、涌泥。该洞段由于水泥浆液可灌性差等原因,还需进行化学灌浆。施工过程中,针对实际情况采用了适宜的灌浆参数和正确的施工工艺,并实施了多种有效的灌浆质量检测方法,取得了较好的效果。Geologic conditions of headrace tunnel middle horizontal section in Class V surrounding rock is very complicated at Qingyuan pumped storage power station in Guangdong province. Sand and mud boiling were appeared during bore drilling. Due to poor groutability of cement grout,chemical grouting is required in this tunnel section. During construction,proper grouting parameters and correct construction technique are used according to real conditions and many effective grouting quality inspections are carried out,gaining good results.

关 键 词:V类围岩 灌浆参数 施工工艺 质量检查 清远抽水蓄能电站 

分 类 号:TV543[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象