Analysis and Countermeasure of The Problem in Inverse Power Supply Test for Pumped-storage Power Station

在线阅读下载全文

作  者:高翔 吕滔 

机构地区:[1]国网新源控股有限公司技术中心,北京市100161

出  处:《水电与抽水蓄能》2017年第3期84-87,共4页Hydropower and Pumped Storage

摘  要:受自身特点影响,抽水蓄能电站的系统倒送电启动试验存在重大隐患。在倒送电启动试验中,保护装置无法进行带负荷校验,其可靠性无法得以验证,一旦并网投运,将对电网运行及机组调试的安全产生不利影响。本文提出了一种利用试验负载校验保护装置的对策,并通过实例演算论证了其可行性。Due to the characteristic of pumped-storage power station,a big hidden trouble will occur when the inverse power supply test performed. During the inverse power supply,load test can't be carried out for the protection device in power station. The reliability of the protection device can't be verified. Once the power station incorporated into the power grid,the safety of the power grid and the generator unit's start-up test will be threatened. A countermeasure is provided to on-load test the protection device by using testing load,the feasibility of which is demonstrated on the case of a real pumped-storage power station.

关 键 词:倒送电 带负荷校保护 抽水蓄能电站中 

分 类 号:TM312[电气工程—电机]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象