东江引水工程潜在不利因素分析及其补偿测算  

Adverse Effect Analysis and Compensation Estimation of Vibration for Water Diversion Project of Dongjiang Hydropower Station

在线阅读下载全文

作  者:颜勇航[1] 

机构地区:[1]湖南省电力公司东江水电厂,湖南资兴423403

出  处:《湖南电力》2017年第6期25-28,共4页Hunan Electric Power

摘  要:东江引水工程从立项到实施一直缺失对利益影响方的补偿资料及研究,且目前国内外尚无同类电站大规模引水案例可资借鉴。本文结合东江水电站的运行现状及东江引水工程的引水规模,分析其遭遇的不利影响和潜在损失;针对湖南电网结构和所损失电能质量,按同质电能替换补偿方式列出补偿计算公式。Compensation data and research of affected persons of Dongjiang diversion project is absent, and there is no similar large-scale diversion cases for reference which conduct water from a hydro-power station with peak and frequency modulation. Combining the current operation situation of Dongjiang hydro-power station and the scale of Dongjiang diversion project , the paper analyzes the adverse effects and potential losses. Aiming at the structure and loss of power quality of hunan power grid, the paper puts forward the homogeneous compensation formula.

关 键 词:东江水电站 引水工程 不利影响 补偿研究 

分 类 号:F407.61[经济管理—产业经济]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象