某电厂水冷壁温度偏高问题分析及处理  被引量:1

Analysis and Treatment of High Temperature of Water Cooled Wall in One Power Plant

在线阅读下载全文

作  者:黄翔[1] 陶谦[1] 王亚欧[1] 陈波 傅高健 

机构地区:[1]江苏方天电力技术有限公司,南京211102

出  处:《现代制造技术与装备》2017年第12期115-116,共2页Modern Manufacturing Technology and Equipment

摘  要:某电厂的1号锅炉为超超临界直流锅炉,在调试期间出现了水冷壁温度过高的问题,且在燃烧方式改变或负荷增减时均存在超温现象。通过分析发现,测点主要分布在燃烧器喷口边缘区域,取消节流孔圈的方法可以增强水冷壁管对锅炉负荷波动、切磨运行的适应性,高负荷时壁温可下降约40℃,低负荷时壁温可下降约60℃。The No.1 boiler of one power plant is an ultra supercritical once-through boiler. During the debugging process, the temperature of the local measuring point of the water cooled wall is too high, and an over-temperature phenomenon occurs when the combustion mode is changed and the load increases or decreases. It is found that the measuring points are mainly distributed in the edge area of the burner nozzle. By canceling the throttle orifice, the water cooled wall’s operation adaptability can be enhanced when the boiler load fluctuates or the coal pulverizer stops. The wall temperature can be reduced by about 40 ℃ at high load. The wall temperature can be reduced by about 60℃ at low load.

关 键 词:超超临界 调试 水冷壁 节流孔圈 

分 类 号:TM621.2[电气工程—电力系统及自动化]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象