三岔河水电站大坝分期填筑施工技术  

Dam Staged Filling Technologies for Sanchahe Hydropower Station

在线阅读下载全文

作  者:郭继怀[1] 

机构地区:[1]中国水利水电第五工程局有限公司,四川成都610066

出  处:《水力发电》2018年第2期52-54,共3页Water Power

摘  要:为实现电站提前发电,三岔河水电站大坝填筑及面板施工从原设计的一期施工优化为两期进行。通过合理地确定一期大坝施工高程、采用合适的填筑施工技术,大坝填筑及面板施工顺利完成。监测结果表明,大坝分期施工后二期填筑未对一期面板质量造成危害,一期面板混凝土质量、面板渗流量等参数满足设计要求。In order to realize the early generation of power station, the dam filling and face slab pouring of Sanchahe Hydropower Station are optimized from original designed whole-stage construction to two-stage construction. By reasonably determining construction elevation of dam in first stage and adopting suitable filling construction technologies, the dam filling and face slab pouring are successfully completed. The monitoring results show that the second-stage filling of dam does not cause any hazard to the quality of first-stage face slab, and the parameters of concrete quality and seepage of first-stage face slab meet design requirements.

关 键 词:大坝填筑 面板浇筑 分期施工 三岔河水电站 

分 类 号:TV541.1[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象