特殊表土地层条件下长距离缓坡斜井施工技术  被引量:1

Construction technology of long-distance gentle-slope incline shaft under the condition of special topsoil

在线阅读下载全文

作  者:车发明 李忠森 张叔胤 

机构地区:[1]陕西煤业化工建设集团有限公司矿建二公司,陕西西安710021

出  处:《陕西煤炭》2017年第1期118-122,共5页Shaanxi Coal

摘  要:介绍了红柳林煤矿二号进风斜井在陕北毛乌素沙漠边缘特殊表土地层条件下的施工情况,通过优化施工装备、改进施工工艺,解决了特厚砂层、含水砂砾粘土层长距离砌碹、加固等一系列难题,对类似地层条件下的矿井建设具有一定的借鉴意义。Based on the analysis of the special topsoil condition of the edge of the Maowusu Desert in northern Shaanxi and the construction condition of No. 2 air inclined shaft in Hongliulin coal mine,the construction equipments and improving construction technology were optimized,the problems of long-distance reinforcement and arching support for extra thick sand layer and aquiferous gravel clay layer were solved. The results provide some reference significance for the mine construction in similar geological conditions.

关 键 词:长距离砌碹 砂层注浆加固 表土段治水 

分 类 号:TD353[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象