千米立井提升设施中扁尾绳的快速敷设工艺  

Rapid Laying Technology of Flat Tail Rope in Hoisting Unit in Kilometer Vertical Shaft

在线阅读下载全文

作  者:朱礼建 邢德喜 庄付永 吕宝峰 ZHU Lijian1, XING Dexi2, ZHUANG Fuyong1, LYU Baofeng1(1. Shandong Tangkou Coal Industry Co., Ltd., Jining 272055, China; 2. Department of Mechanical and Electrical Engineering, Zibo Mining Group, Zibo 255120, Chin)

机构地区:[1]山东唐口煤业有限公司,山东济宁272055 [2]淄博矿业集团公司机电处,山东淄博255120

出  处:《煤矿机电》2018年第2期103-106,共4页Colliery Mechanical & Electrical Technology

摘  要:国内传统的立井敷设扁尾绳工程中都采用旁井下放罐笼提升敷设,每次只敷设一条尾绳。为加快千米立井提升设备安装工程的进度,敷设扁尾绳的工艺通过采用可变配重,三条尾绳一次性全部敷设完毕,既可提高井筒作业的安全性,又加快了施工速度。通过试用验收,取得了良好的效果。Traditional shaft laying flat tail rope in engineering used sideward well cage hoist laying, only can lay a tail rope at one time. In order to speed up the installation progress of hoisting unit in kilometer vertical shaft, the process of laying flat tail rope was completed by variable counterweight, and three tail ropes can be laid at one time. It not only improved the safety of shaft operation, but also speed up the construction. Through trial acceptance, good results have been achieved.

关 键 词:立井 扁尾绳敷设 可变配重 快速敷设 

分 类 号:TD532[矿业工程—矿山机电]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象