KCROP项目海洋平台陆地调试用临时配电系统设计和组建  被引量:3

Design and Establishment of the Temporary Power System on Ocean Platform of KCROP Project

在线阅读下载全文

作  者:丁杰[1] 陈丽[1] 张晶[1] 耿恒业 王晓迪[1] DING Jie;CHEN Li;ZHANG Jing;GENG Heng-ye;WANG Xiao-di(Offshore Oil Engineering Co., Ltd., Tianjin 300452, Chin)

机构地区:[1]海洋石油工程股份有限公司,天津300452

出  处:《机电工程技术》2018年第3期155-158,共4页Mechanical & Electrical Engineering Technology

摘  要:以国外项目KCROP项目海洋石油平台陆地调试为例,重点阐述了保障陆地调试工作最大化情况下480 V、60 Hz临时配电系统的设计与组建,包括临时用电设备、电缆的选取、电缆敷设及送电试验的整个过程。该系统确保了该项目陆地调试工作的安全、顺利进行,保障了组块出海里程碑点的实现,同时为后续类似同类型项目临时配电系统的设计提供借鉴。Taking the temporary power system of an overseas project-KCROP (KHAFJI Crude Related Offshore Project) for example, the paper briefly introduces the design and composition of 480V/60Hz temporary power system, including temporary equipment, cable, laying and power transmission test, etc. The system ensures the safety and smooth operation of the onshore commissioning work of the project, ensures the realization of the milestone of the project, and provides reference for the design of the temporary distribution system similar to the same type of project.

关 键 词:海洋平台 陆地调试 临时配电系统 

分 类 号:TM726[电气工程—电力系统及自动化]

 