作 者:刘瑞 LIU Rui(The 5th Engineering Co., Ltd., China Railway 18th Bureau Group,Tianjin 300350, China)
机构地区:[1]中铁十八局集团第五工程有限公司,天津300350
出 处:《长春大学学报》2018年第4期7-11,共5页Journal of Changchun University
摘 要:当桥梁跨越不可间断的运输线(铁路、公路、河道等),由于交通线路运营繁忙或场地限制,其它施工方法无法满足要求时,采用顶推法或转体法施工从空中完成跨越作业,无疑是一种比较理想的方法。大跨度钢管拱桥顶推施工,通过滑块限位、导向纠偏装置、顶推千斤顶顶力纠偏方式,分段施工,减少了顶推重量,缩短了顶推段现浇梁占用相邻现浇段时间,即解决了跨度大的难题,又减小了顶推重量,缩短了工期。When bridges span unbroken transportation lines( railways,highways,river channels,etc.),due to the busy traffic lines or site restrictions,many construction methods can not meet the requirements,it is undoubtedly an ideal method to perform a spanning from the air by using incremental launching method or swivel-type method. The incremental launching technology for long-span steel pipe arch bridges is a method that uses spacing sliding block,guiding correction device and jack to correct the errors.This is a segmental construction technology,which reduces the push weight and shortens the push segment time of adjacent cast-in-place occupied by cast-in-situ beams. It not only solves the problem of long span,but also reduces the push weight,shortening the construction period.
分 类 号:U445.462[建筑科学—桥梁与隧道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:3.137.185.239