作 者:徐华生[1] 杨龙 XU Hua-sheng1, YANG long2(1.Production Department, Huainan Mining Group Corporation, Huainan 232001 ,China; 2. School of Civil Engineering and Architecture, Anhui University of Science and Technology, Hnainan 232001, Chin)
机构地区:[1]淮南矿业集团公司生产部,安徽淮南232001 [2]安徽理工大学土木建筑学院,安徽淮南232001
出 处:《煤炭技术》2018年第6期110-113,共4页Coal Technology
基 金:安徽理工大学创新基金资助项目(2017CX2070)
摘 要:基于潘三矿新西风井表土段整体稳定性差的特点,决定采用冻结法施工井筒,并进行冻结参数和冻结方案的设计。冻结结果表明:积极冻结期盐水温度均低于设计温度;冻结时间比设计时间提前7 d,冻结壁厚度和冻结壁温度达到设计值;冻结管工作状态正常,矿井正常施工未受到影响。Based on the poor stability of the surface soil section of the new west ventilation shaft in Panji No.3 mine, decided to use the freezing method to construct the wellbore and to design the freezing parameters and freezing scheme. The freezing results show that the freezing temperature is lower than the design temperature. The freezing time is 7 days ahead of the design time, the freezing wall thickness and temperature reach the design value. The working condition of the freezing pipe is normal, the normal construction is not affected.
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.219