纳林庙灾害治理项目治理首区工作线长度优化  

Length optimization of working line in Nalinmiao hazard control project first area

在线阅读下载全文

作  者:顾冬冬 王华 呼和 GU Dongdong;WANG Hua;HU He(Inner Mongolia Yitai Cool Co.,Ltd.Inner MogoliaErdos 017000)

机构地区:[1]内蒙古伊泰煤炭股份有限公司,内蒙古鄂尔多斯017000

出  处:《露天采矿技术》2018年第4期11-14,共4页Opencast Mining Technology

摘  要:为尽快现实纳林庙煤矿老采空区灾害集中连片综合治理成果,增加露天开采的工作线长度是缩短治理周期最直接、有效的技术措施,在确定经济工作线长度时,必须结合煤层赋藏条件、生产模式、开采工艺、工作帮水平推进速度及内排土运距等因素统筹考虑,利用3DMine三维建模软件计算在不同的4-2~#煤采空工作线长度下形成最终开采边界的工程量,分析不同工作线长度与平均剥采比、剥离费用吨煤成本之间的关系,确定经济工作线长度。In order to complete Nalinmiao geological hazard control project as soon as possible, increasing the length of working line is the most direct and effective way of shortening project cycle. When determining the length of working line, the company considers the coal seam mining condition, production patterns, mining technology, the advancing speed of working bench and the dumping transport distance, this article analyzes the relationship between different length of working line and average stripping radio, the stripping cost of coal by using 3D modeling software to calculate the amount of engineering of the final mining boundary under different 4-2~# coal working line length.

关 键 词:工作线长度 吨煤成本 模拟开采 

分 类 号:TD824[矿业工程—煤矿开采]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象