基于多Agent仿真的移动防洪系统应急安装研究  被引量:7

Research on Emergency Installation of Mobile Flood Control System Based on Multi-Agent Simulation

在线阅读下载全文

作  者:汪伦焰 翟啸东 李慧敏 张婵 吕乐琳 WANG Lunyan;ZHAI Xiaodong;LI Huimin;ZHANG Chan;LYU Lelin(School of Water Resources,North China University of Water Resources and Electric Power,Zhengzhou 450046,China;Water Environment Governance and Ecological Restoration Academician Workstation of Henan Province,Zhengzhou 450002,China)

机构地区:[1]华北水利水电大学水利学院,河南郑州450046 [2]河南省水环境治理与生态修复院士工作站,河南郑州450002

出  处:《人民黄河》2018年第11期38-43,共6页Yellow River

基  金:2017年度河南省高校科技创新人才支持计划项目(2017-CX-023);2016年河南省科技厅"产学研"项目(162107000051)

摘  要:移动式防洪系统是一种具备高安全性的标准化防洪方法,但在中国城市防洪系统中应用还不多,对其应急安装管理研究不足是制约因素之一。依托某市的移动式防洪墙工程,对其安装过程进行施工组织设计,构建了移动式防洪系统应急安装数学规划模型,利用Anylogic软件对移动式防洪墙构件的装载、运输过程进行仿真,利用仿真结果对该数学规划模型进行求解,并给出最优方案。研究表明:通过资源的合理调配,改进施工步骤,可以缩短移动式防洪墙的应急安装时间,为防洪抢险赢得宝贵时间。Mobile flood control system is a method with high security standard of flood control, but in China, thereis few city flood control system application and the lack of emergency management research installation is one of the constraints. Relying on one mobile flood control wall engineering, this paper conducted the construction design of its installation process and built a mobile emergency flood control system installation mathematical programming model. It used Anylogic software to simulate the loading and transport process of mobile flood wall components, simulated the mathematical planning model through simulation results and gave the optimal solution. The research shows that through reasonable deployment of resources and improvement of construction procedures, it is possible to shorten the emergency installation time of mobile flood walls and win valuable time for flood prevention and rescue.

关 键 词:移动式防洪系统 整数规划 应急安装 建模仿真 

分 类 号:F224[经济管理—国民经济] TV87[水利工程—水利水电工程]

 