基于动态规划算法的人行天桥施工组织优化设计  

Optimized Design of Construction Organization of Pedestrian Bridge Based on Dynamic Programming

在线阅读下载全文

作  者:张博 ZHANG Bo(China Railway 4th Bureau Group Road and Bridge Engineering Co.,Ltd.,Changchun 130052,China)

机构地区:[1]中铁四局集团路桥工程有限公司,长春130052

出  处:《价值工程》2018年第9期221-223,共3页Value Engineering

摘  要:在跨铁路桥梁施工中,修建人行天桥是满足施工人员通行和材料的转运的必要措施。以长春铁路综合货场工程为例,根据此工程人行天桥施工工期特征,基于动态规划算法将人行天桥的施工过程划分为3个阶段,每个阶段为一周,建立了动态规划数学模型,并对模型进行求解,获得了施工费用最低时的施工工序,有效降低了施工费用,具有一定的工程应用性。In the construction of cross-railway bridges,the construction of pedestrian bridge is a necessary measure to meet the construction workers'access and material transfer.Taking the Changchun Railway Complex freight yard project as an example,according to the characteristics of this project pedestrian bridge construction period,the construction process of the pedestrian bridge is divided into three stages based on the dynamic programming algorithm.Each stage is one week,the dynamic programming mathematical model is established,and the model is solved to get the construction process at the lowest construction cost,effectively reducing the construction cost,so it has a certain degree of engineering applicability.

关 键 词:铁路跨线桥 人行天桥 动态规划算法 施工组织优化 

分 类 号:U445[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象