鞍钢鲅鱼圈1号高炉停炉实践  被引量:3

Blowing out practice of No.1 blast furnace in Ba Yuquan of Ansteel

在线阅读下载全文

作  者:佟溥昊 戴永燕[1] 蒋益[2] 黄菊 白欣 Tong Puhao;Dai Yongyan;Jiang Yi;Huang Ju;Bai Xin(Education and Training Center,Anshan Iron and Steel Group Corporation;Bayuquan Branch Angang Steel Co.,Ltd)

机构地区:[1]鞍山钢铁集团公司教育培训中心 [2]鞍钢股份有限公司鲅鱼圈钢铁分公司

出  处:《冶金能源》2018年第2期7-10,共4页Energy For Metallurgical Industry

摘  要:文章针对鞍钢鲅鱼圈1号高炉停炉过程的方法进行总结和介绍。通过对其休风料的准备,预休风过程等准备方法,以及停炉过程中对风量、水量、富氧、炉顶温度、煤气组成等控制实现了安全停炉的目的。整个过程共用时20h15min。The method of blowout the furnace of No.1 blast furnace in Ba Yuquan of Ansteel was introduced.Through the preparation method of the preparation of its off wind material has been pre off the wind process,and the control of air volume,water quantity,oxygen enrichment,top temperature and gas composition in the process of stopping,the purpose of safe shutdown was achieved.The whole process of blowout the furnace was shared 20h15min.

关 键 词:大型高炉 降料线 停炉 

分 类 号:TF548[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象