超大使用荷载条件下沉箱码头针对性设计施工  

Specific design and construction of caisson wharf under extreme heavy load

在线阅读下载全文

作  者:龙海飚 刘丽芬 LONG Hai-biao;LIU Li-fen(CCCC Fourth Harbor Engineering Co.,Ltd.,Guangzhou 510231,China)

机构地区:[1]中交第四航务工程局有限公司,广东广州510231

出  处:《水运工程》2018年第11期214-218,共5页Port & Waterway Engineering

摘  要:超大使用荷载条件下保证码头稳定并严格控制工后沉降位移是设计施工难题。厦门港招银港区10号泊位码头区域承受最大300 kN/m^2垂直均布荷载,配置起重能力达26 MN的移动式高空吊。针对该超大使用荷载条件,设计施工了单重5 800 t带剪力键的大沉箱、16 000 m^3整体式钢筋混凝土大平台、顶宽达41 m的超宽棱体,针对严格控制码头工后沉降位移要求,对码头主体实施了堆载预压。码头工后效果达到预期。It is a difficult problem for the design and construction of a wharf to guarantee the wharf stability and strictly control the post-construction settlement and displacement under super-large service load.The wharf area at berth No.10 in Zhaoyin harbor district of Xiamen Port is subjected to up to 300 kN m 2 vertical uniformly distributed load,and equipped with the mobile overhead crane with a lifting capacity of 26 MN.For the super-large service load,a large-scale 5 800 t caisson with shearing key,16 000 m 3 reinforced concrete platform and super-wide gengon with 41 m top width are designed and constructed.Pertaining to the requirements of strictly controlling the post-construction settlement and displacement of the wharf,the surcharge preloading is implemented for the main part of the wharf,and the post-construction effect reaches the expectation.

关 键 词:超大使用荷载 沉箱码头 施工 沉降 位移 

分 类 号:U653.5[交通运输工程—港口、海岸及近海工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象