煤矿特大装载硐室施工工艺探究——以麻家梁矿为例  

Research on Construction Technology of Extra Large Loading Chamber in Coal Mine:Taking Majialiang Mine as an Example

在线阅读下载全文

作  者:解志朝 乔志 XIE Zhi-chao;QIAO Zhi(Shanxi Huajin Hanzui Coal Industry Co.,Ltd.,Linfen 041000,China)

机构地区:[1]山西华晋韩咀煤业有限责任公司,临汾041000

出  处:《价值工程》2019年第3期116-118,共3页Value Engineering

摘  要:麻家梁矿主立井箕斗装载硐室为新型特大装载硐室。该装载硐室设计比较复杂,为双侧通过式,总高度41m,硐室总掘进体积5707m3,浇筑混凝土量1060m3,计划工期106天,经过优化施工方案,合理组织施工,该硐室在安全无事故和质量全优的情况下共用工期51天,比计划工期提前了55天,创出了硐室施工新记录。The main vertical shaft dumping chamber of Majialiang Mine is a new type of extra large loading chamber.The design of the loading chamber was complicated.It was a double-pass type with a total height of41meters,a total digging volume of5707m^3,a concrete volume of1060m^3,and the planned construction period was106days.After optimizing construction plan and with reasonable construction organization,the chamber was completed in51days in the case of no accidents and excellent quality,55days ahead of the planned construction period,creating a new record of chamber construction.

关 键 词:特大装载硐室 优化施工方案 硐室施工新记录 

分 类 号:TD264[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象