汉钢1080m^3高炉喷涂造衬开炉生产实践  

Blow-in Production Practice of Spraying Lining of 1080 m^3 Blast Furnace at Hansteel

在线阅读下载全文

作  者:冯磊 侯向平 Feng Lei;Hou Xiangping(Shaanxi Iron & Steel Group Hanzhong Iron & Steel Co.,Ltd.,Mianxian Shaanxi 724200)

机构地区:[1]陕钢集团汉中钢铁有限责任公司,陕西勉县724200

出  处:《山西冶金》2019年第1期90-91,108,共3页Shanxi Metallurgy

摘  要:汉钢1080m^3高炉于2015年2月10日停炉中修,3月20日20:08点火送风;开炉前扒除铁口周围的焦炭、选择合适的开炉方案及送风前热风管道的预热等一系列措施,高炉从点火到达产仅有时3d,各项经济指标迅速达标。1080 m3 BF of Hansteel was shut down and repaired on February 10, 2015, and was ignited at 20:08 on March 20. A series of measures, such as removing coke around the iron-notch, choosing the appropriate start-up scheme and preheating the hot air pipeline before blowing, were taken before the start-up. The BF reached its production only 3 days after ignition, and the economic indicators quickly reached the standard.

关 键 词:高炉 铁口 开炉方案 经济指标 

分 类 号:TF576.7[冶金工程—钢铁冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象