超浅埋暗挖隧道下穿河道施工技术研究  被引量:2

Research on the Construction Technology of Undercrossing River of Super-Shallow Buried Tunnel

在线阅读下载全文

作  者:高伟强 GAO Wei-qiang(China Railway 23 Bureau Group No.3 Engineering Co. Ltd.,Chengdu 611130,China)

机构地区:[1]中铁二十三局集团第三工程有限公司,成都611130

出  处:《中小企业管理与科技》2019年第12期150-151,共2页Management & Technology of SME

摘  要:双线铁路隧道超浅埋下穿山谷河道时施工安全风险极高,主要有大断面、富水、地质条件差、超浅埋的特点。采用三台阶七步开挖和拱部护拱备用方案相结合的施工方法,加强超前支护和初期支护,最大限度减少对围岩的扰动,安全顺利地通过超浅埋段。论文对格鲁吉亚现代化铁路项目新建T7隧道下穿超浅埋河道施工进行了介绍,为今后同类型隧道施工提供参考。The construction safety risk of the double line railway tunnel is very high when it is buried under the valley and river channel, which mainly has the characteristics of large cross-section, rich water, poor geological conditions and super-shallow burial. The construction method of three-step and seven-step excavation combined with the spare plan of arch protection is adopted to strengthen the advanced support and the initial support, minimize the disturbance to the surrounding rock, and safely and smoothly pass through the ultra-shallow buried section. This paper introduces the construction of new T7 tunnel under the ultra-shallow buried channel in the modern railway project of Georgia, and provides reference for the same type of tunnel construction in the future.

关 键 词:超浅埋 大断面 富水 地质条件 

分 类 号:U455.4[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象