采用可移动式分支溜槽浇筑大体积混凝土的施工方法  被引量:1

BRIEF DISCUSSION ON METHOD OF POURING MASS CONCRETE WITH MOVABLE BRANCH CHUTE

在线阅读下载全文

作  者:刘帅[1] 白峰振 张瑜[1] 胡林 徐国庆[1] LIU Shuai;BAI Feng-zhen;ZHANG Yu;HU Lin;XU Guo-qing(China Construction Second Engineering Bureau Ltd.,100010,Beijing,China)

机构地区:[1]中国建筑第二工程局有限公司

出  处:《建筑技术》2019年第10期1237-1239,共3页Architecture Technology

摘  要:昆明春之眼商业中心副塔楼筏板基础浇筑量达1.4万m^3混凝土,为保证连续有效高效地浇筑混凝土,在基坑狭窄空间内采用可移动式分支溜槽.可移动式分支溜槽施工效率高,适用范围广,节约了固定式溜槽分支搭设的成本,又避免了混凝土浇筑不连续带来的质量问题.The annex tower building of Kunming Chunzhiyan (Eye of Spring) Commercial Center has a raft foundation with 14000 m^3 concrete placing volume. To guarantee continuous and effective concrete placing, removable bypass chute was used for narrow spaces in the foundation pit. The removable bypass chute has high construction efficiency and wide application scope, not only saving the construction cost of fixed bypass chute installation, but also avoiding quality problems due to discontinuous concrete placement.

关 键 词:深基坑 浇筑大体积混凝土 可移动式分支溜槽 

分 类 号:TU745.3[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象