黄登水电站水库初期蓄水方案研究  被引量:9

Research on Initial Water Storage Scheme of Resevoir in Huangdeng Hydropower Station

在线阅读下载全文

作  者:罗智锋 杨子俊 周林 LUO Zhi-feng;YANG Zijun;ZHOU Lin(Power China Kunming Engineering Corporation Limited,Kunming 650051,China)

机构地区:[1]中国电建集团昆明勘测设计研究院有限公司

出  处:《云南水力发电》2020年第1期88-91,共4页Yunnan Water Power

摘  要:在充分考虑并分析黄登水库初期蓄水期间大坝施工、库区移民等工程形象面貌要求以及下游生态、航运、电站发电等综合利用用水需求多种因素,拟定黄登电站初期蓄水方案,提出相关建议,可操作性强,并较好地应用于实际蓄水过程。In this paper,the engineering appearance requirements of dam construction and resettlement engineering during the initial impoundment of Huangdeng Reservoir were fully consider and analyze,considering the water demands of ecological,shipping and power generation in downstream,the initial impoundment scheme of Huangdeng Hydropower Station was formulate.The scheme has been summarized and suggestions were made,which can be used as reference for similar projects.

关 键 词:初期蓄水 综合利用 黄登水电站 多种因素 

分 类 号:TV62+2[水利工程—水利水电工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象