铜陵新建顶吹炉项目试生产实践  被引量:2

The Trial Production Practice of a New Top Blowing Furnace Project in Tongling

在线阅读下载全文

作  者:程利振 CHENG Lizhen(Tongling Nonferrous Metals Group Holdings Co.,Ltd.,Tongling,Anhui,244100,China)

机构地区:[1]铜陵有色金冠铜业分公司,安徽铜陵244100

出  处:《有色冶金设计与研究》2020年第2期18-20,23,共4页Nonferrous Metals Engineering & Research

摘  要:详细介绍了铜陵有色新建顶吹炉项目熔炼主工艺的工艺流程,以及配料、制粒、熔炼、水淬的4个工序的工艺特点。针对新建顶吹炉试生产过程中出现的问题,提出了相应的改进方法,有效稳定了顶吹炉渣型、冰铜品位和冶炼温度。该项目自2018年5月18日开始投料试生产以来,运行情况良好,且质量好、投资省、达产快,安全环保。This paper introduces in detail the main smelting process of the new top blowing furnace project of Tongling Nonferrous Metals Co., Ltd., as well as the technological characteristics of the four processes of batching,?pelletizing, smelting and water quenching. In view of the problems in the trial production of the new top blowing furnace, the corresponding improvement methods are put forward, which effectively stabilize the slag type, matte grade and smelting temperature of the top blowing furnace. Since the trial production of the project started on May 18, 2018, it has been running well with good quality, low investment, fast production, safety and environmental protection.

关 键 词:试生产 顶吹 喷枪 流程 

分 类 号:TF811[冶金工程—有色金属冶金]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象