“整体下放逐级分段拆除”的网架拆除施工技术  

Construction Technology of Dismantling the Net Frame of "Overall Down and Dismantling Step by Step"

在线阅读下载全文

作  者:蔡广东 CAI Guang-dong(Fujian Hetong Construction Co.Ltd.,Fuzhou 350000,China)

机构地区:[1]福建和通建筑工程有限公司,福州350000

出  处:《工程建设与设计》2020年第8期177-178,共2页Construction & Design for Engineering

摘  要:某工程钢屋盖网架拆除现场条件局促,内场大型汽车吊无法进入。为确保拆除进度和施工安全,屋顶网架采取"整体下放逐级分段拆除"的施工技术。该方法省去了施工平台的搭设工作,大大减少了高空作业量,提高了施工效率,保证了施工进度,达到了既定的施工目标要求。A project steel roof frame demolition site conditions of a project are limited, the large car crane can not enter the field. In order to ensure the progress of demolition and construction safety, the roof grid adopts the construction technology of "overall down and dismantling step by step ". The method saves the construction platform construction work, greatly reduces the amount of work at high altitude, improves the construction efficiency, guarantees the construction progress, and achieves the established construction target requirements.

关 键 词:大跨度网架 提升搭架 逐级分段 网架拆除 

分 类 号:TU746.5[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象