综采工作面过陷落柱深孔预注浆加固技术  被引量:4

Technology of Pre-injection Reinforcement for Deep Hole of Collapse Column in Fully Mechanized Mining Face

在线阅读下载全文

作  者:王凯 Wang Kai(Chengzhuang Mine,Jincheng Lanyan Coal Industry Co.,Ltd.,Shanxi Jincheng 048000)

机构地区:[1]晋城蓝焰煤业股份有限公司成庄矿生产技术部,山西晋城048000

出  处:《山东煤炭科技》2020年第5期49-50,53,共3页Shandong Coal Science and Technology

摘  要:针对成庄矿5308大采高工作面过陷落柱影响区域大概率出现片帮冒顶等问题,采用超前深孔注浆加固破碎带煤体,通过确定合理的注浆孔布置参数、注浆工艺,确保工作面正常回采作业。实践表明,经过预注浆处理后,陷落柱影响区域煤体强度得到有效加强,有效防止了架前片帮和冒顶,取得了良好的经济效益。In order to solve the problem that the 5308 working face of Chengzhuang Coal Mine passes through the area affected by the collapse pillar and the roof falls,the advanced deep hole grouting is adopted to reinforce the coal body in the broken zone,and the normal mining operation of the working face is ensured by determining the reasonable grouting hole layout parameters and grouting technology.The practice shows that after pre grouting treatment,the strength of the coal body in the area affected by the collapse column is effectively strengthened,the front wall and roof fall are effectively prevented,and good economic benefits are obtained.

关 键 词:综采 陷落柱 注浆 加固 

分 类 号:TD265.4[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象