轨道交通地下站上盖物业前期介入要点分析  

Analysis the Key Points of Early Intervention of Upper Cover Property of Underground Station of Rail Transit

在线阅读下载全文

作  者:樊鸿伟 FAN Hongwei(Shanghai Pudong Development Group Co.,Ltd.,Shanghai 201204,China)

机构地区:[1]上海浦东开发(集团)有限公司,上海201204

出  处:《建筑施工》2020年第5期892-893,896,共3页Building Construction

摘  要:以上海轨交14号线地铁昌邑路站1、2号口附属项目为例,结合地铁上盖物业与地铁设施的公用结构,介绍了地铁附属配套设计过程中的具体预留内容。通过在地铁上盖物业项目的设计过程中,提前进行相关结构的预留,减少了上盖项目建设过程中的加固量,节约了上盖物业建设时间、物料、资金,相关的经验可为类似项目提供借鉴。Taking the auiliary project of entrance No.1 and No.2 of Changyi Road Station of Shanghai rail transit line 14 as an example,combined with the public structures of subway upper cover property and subway facilities,the specific reserved contents in the auxiliary design process of the subway are introduced.In the design process of subway upper cover property project,the reservation of relevant structures shall be carried out in advance.It reduces the amount of reinforcement in the construction process of subway upper cover project and saves the construction time,materials and funds of the upper cover property.The relevant experience can provide reference for similar projects.

关 键 词:轨道交通地下站 上盖物业 开发条件预留 整体设计 

分 类 号:TU71[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象