田湾核电放射性废物处理中心调试  

Commissioning of Raioactive Waste Treatment Center at Tianwan NPP

在线阅读下载全文

作  者:马小强 张祥贵[1] 许建军[1] 陆元志[1] MA Xiao-qiang;ZHANG Xiang-gui;XU Jian-jun;LU Yuan-zhi(Jiangsu Nuclear Power Corporation,Lianyungang,Jiangsu Prov.222000,China)

机构地区:[1]江苏核电有限公司,江苏连云港222000

出  处:《中国核电》2020年第2期254-258,共5页China Nuclear Power

摘  要:田湾核电放射性废物处理中心(T4UKT)是田湾核电放射性废物集中处理设施,设计为田湾1~6号机组服务。由于工程滞后,系统调试进度压力较大。通过安装、调试优化,有效缩短了工期,系统实际调试工期5个多月,不到国内同类设施实际调试工期的三分之一。本文简单介绍了T4UKT主工艺系统和调试经验,以及调试期间主要缺陷处理。The radioactive waste treatment center(T4UKT)of Tianwan NPP is a centralized radioactive waste treatment facility,and designed to treat the radioactive waste from Units 1~6.T4UKT equipment installation schedule is delayed over 6 month,and the commissioning schedule has to be shorted.Through installation and commissioning optimization,the actual commissioning period is only 5 months,less than one third of the actual commissioning period of similar project in China.This paper briefly introduces the T4UKT radioactive waste treatment process and system commissioning with non-radioactive waste,as well as the main issues during system commissioning.

关 键 词:核电厂 放射性废物处理中心 调试 放射性废物 

分 类 号:TL941[核科学技术—辐射防护及环境保护]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象