高地应力软岩大变形隧道内轨道工程接口设计探讨  被引量:2

Discussion on Interface Design of Track Construction in Soft Rock Large Deformation Tunnel

在线阅读下载全文

作  者:刘喆丰 田春香[1] 李粮余[1] 黎旭[1] LIU Zhefeng;TIAN Chunxiang;LI Liangyu;LI Xu(China Railway Eryuan Engineering Group Co.,Ltd.,Chengdu 610031,China)

机构地区:[1]中铁二院工程集团有限责任公司,成都610031

出  处:《高速铁路技术》2020年第5期82-86,共5页High Speed Railway Technology

摘  要:西南艰险山区铁路选线受地形限制,往往以隧道形式通过。山区隧道埋深大、区域构造强烈、地质条件复杂,高地应力、较强残余构造应力、断层破碎带、涌水等问题普遍存在。复杂的地质环境加上施工过程中的诸多干扰因素极易引起围岩大变形,大变形不仅增加施工难度,处置措施不当还将引起的隧底变形和无砟轨道上拱等问题。针对这一问题,本文以现有隧道软岩大变形的机理为讨论依据,着重分析了大变形对隧道和轨道工程的影响,指出了现行设计接口中的局限性,提出了相应的解决措施和建议。Railway in southwest dangerous mountainous areas is limited by topography for location,and often passes through tunnels.For tunnels in mountainous areas,deep-buried depth,strong regional structures,complex geological conditions,high ground stress,strong residual tectonic stress,fault fracture zones,water gushing and other problems are common.Complicated geological environment and many interference factors during the construction can easily cause large deformation of surrounding rock,which not only increases the difficulty of construction,but also leads to deformation of the tunnel bottom and arch on ballastless track due to improper treatment measures.To solve this problem,based on the mechanism of large deformation of soft rock in existing tunnels,in the paper,the influence of large deformation on tunnel and track construction is emphatically analyzed,the limitations in the current design interface are described,and corresponding solutions and suggestions are proposed.

关 键 词:软岩大变形 接口设计 沉降评估 

分 类 号:U456.3[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象