交互式快速换绳在小庄煤矿主井换绳的应用研究  

Application of Interactive Fast Rope Changing in Main Shaft of Xiaozhuang Coal Mine

在线阅读下载全文

作  者:刘昌国 董红涛 刘坤亮 LIU Changguo;DONG Hongtao;LIU Kunliang(Shaanxi Binchang Xiaozhuang Mining Co.,Ltd.,Xianyang Shaanxi 713500)

机构地区:[1]陕西彬长小庄矿业公司,陕西咸阳713500

出  处:《智能建筑与工程机械》2020年第6期111-112,共2页Intelligent Building and Construction Machinery

摘  要:立井提升系统首绳更换是立井提升系统管理中一项工作量大、工作条件艰难、工作风险大的关键施工工作。传统的首绳更换作业通常需要3~5 d,而采用交互式快速换绳则只需要8~10 h便可完成,本文结合我矿更换主井提升2#系统更换首绳和悬挂装置施工作业,介绍了交互式快速换绳的应用及工作要点,以期进一步提高小庄煤矿主井换绳效率。The first rope replacement of shaft hoisting system is a key construction work with heavy workload,difficult working conditions and high risk in the management of shaft hoisting system.The traditional first rope replacement operation usually takes 3~5 days,while the interactive fast rope replacement only takes 8~10 hours.This paper introduces the application and key points of interactive fast rope replacement based on the replacement of head rope and suspension device of hoisting 2 system in main shaft of Xiaozhuang coal mine,so as to further improve the efficiency of rope replacement in Xiaozhuang coal mine.

关 键 词:立井提升 首绳更换 交互式 快速 

分 类 号:TD53[矿业工程—矿山机电]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象