建井期间竖井多中段提升施工方案研究  被引量:1

Study on the Construction Scheme of Multi-middle Shaft Lifting During Construction

在线阅读下载全文

作  者:吕芳飞 LV Fang-fei

机构地区:[1]金诚信矿业管理股份有限公司,北京100070

出  处:《有色设备》2020年第6期27-31,共5页Nonferrous Metallurgical Equipment

摘  要:在整个矿山建设工程中,竖井施工结束后,由竖转平施工中段及溜破系统等工程成为制约建井工期的关键因素。由于各个矿山的特点和要求不同,对于无法立即进行井筒永久装备的工程来说,此时利用凿井期间的施工装备来施工中段工程就成了建设及施工单位的共同选择。对于非煤矿山而言,大量无轨设备的使用使得罐笼+有轨矿车运输提升成为了过去式,同时,多中段同时施工也给矿井提升系统带来各种问题,如何保证多中段同时施工的提示系统安全运转,也就成为了一个新的课题。In the whole mine construction project,after the completion of the shaft construction,from the vertical to the horizontal construction of the middle section and slip system and other projects become the key factors restricting the construction period of the well.Due to the different characteristics and requirements of each mine,it is a common choice for the construction and construction units to use the construction equipment during the sinking period to carry out the mid-course construction project for the projects that cannot be carried out immediately with permanent wellbore equipment.For non-coal mines,the use of a large number of trackless equipment makes the hoisting of cage+railcar transport become the past.At the same time,the simultaneous construction of multiple middle sections also brings various problems to the mine hoisting system.How to ensure the safe operation of the prompt system for the simultaneous construction of multiple middle sections has become a new topic.

关 键 词:竖井 竖转平施工 临时改绞 无轨化施工 多中段提升 

分 类 号:TD633[矿业工程—矿山机电]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象