作 者:杨林 汤荣平 阿拉腾布日固德 王永新 TANG Rong-ping;Aratenburigud;YANG Lin;WANG Yong-xin(Huaneng Lancang River Hydropower Co.,LTD.,Kunming 650214,China)
机构地区:[1]华能澜沧江水电股份有限公司,云南昆明650000
出 处:《云南水力发电》2021年第2期182-184,共3页Yunnan Water Power
摘 要:里底水电工程三期溢洪道改建要求在1个枯期内完成,工期较为紧张,三期改建是否能按期完成,关系着电站按期投产发电目标。因此,对三期工程的全过程施工管理研究显得非常重要。从建设管理出发,充分阐述了优化、管理措施方面取得的经验,对全过程管理经验进行了详细介绍。Reconstruction of the third-stage spillway of Lidi Hydropower Project is required to be completed in one dry period,and the construction period is rather tight.Whether the third-stage reconstruction can be completed on schedule is related to the target of putting the power plant into operation on schedule.Therefore,it is very important to study the whole construction management of PhaseⅢProject.Starting from construction management,the experience gained in optimization and management measures is fully elaborated,and the whole process management experience is described in detail.
分 类 号:TV651.1[水利工程—水利水电工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.171