R-550D自升式钻井平台升降系统的调试  被引量:1

Jacking System Commissioning Difficulties and Solutions of R-550D Jack-up Drilling Platform

在线阅读下载全文

作  者:段谟簿 练博强 蓝巨滔 DUAN Mobu;LIAN Boqiang;LAN Jutao(CSSC Huangpu WenChong Shipbuilding Co.,Ltd.,Guangzhou 510715)

机构地区:[1]中船黄埔文冲船舶有限公司,广州510715

出  处:《广东造船》2021年第1期71-74,78,共5页Guangdong shipbuilding

摘  要:R-550D自升式钻井平台中采用电动齿轮式升降系统,该系统由多个升降模块构成,均匀分布在各桩腿两侧。自升式平台在下水后,依靠其升降系统进行站桩作业,以方便码头舾装的进行。因此,升降装置需在下水后进行联调试验,以确保其尽快达到可使用状态。The R-550D jack-up drilling platform adopts electric gear jacking system,which is composed of several jacking units and evenly distributed on both sides of each pile leg.After launching the jack up platform needs to rely on its jacking system for pile operation,so as to facilitate the outfitting at wharf.Therefore,the jacking device should be jointly commissioned after launching to ensure that it could be used as soon as possible.This paper discusses the commissioning difficulties and solutions of the jacking system of the R-550D jack-up drilling platform.

关 键 词:升降系统 组成 调试 

分 类 号:U674.38[交通运输工程—船舶及航道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象