国华盘山输煤系统PLC改造为DCS控制  被引量:4

Transformation of Coal Handling System PLC Guohua Panshan into DCS Control

在线阅读下载全文

作  者:吴松涛 李锐成[1] 张国栋 

机构地区:[1]杭州和利时自动化有限公司,浙江杭州310018

出  处:《自动化博览》2021年第3期78-80,共3页Automation Panorama1

摘  要:天津国华盘山发电有限责任公司输煤系统采用的是PLC控制系统,于1999年改造,已经运行超过18年,I/O模块以及网络通讯等故障多发,为保证系统安全运行,将该输煤控制系统更换为DCS系统控制。本次输煤控制系统改造为“在线”升级改造方式。本文通过该项目系统设计及调试过程中遇到的问题处理进行介绍,为后续类似改造项目提供借鉴。The coal handling system of Tianjin Guohua Panshan Power Co., Ltd adopts PLC control system, which was reformed in 1999 and has been in operation for more than 18 years. There are many I/O modules and network communication failures. In order to ensure the safe operation of the system, the coal handling system is replaced with DCS system control. It was transformed into an "online" upgrade mode. This paper introduces the problems encountered in the system design and debugging process of the project, and provides reference for the similar projects.

关 键 词:分散控制系统(DCS) PLC 火电厂 改造 

分 类 号:TP273[自动化与计算机技术—检测技术与自动化装置]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象