井巷贯通测量方案及精度控制分析  被引量:6

Analysis on the Scheme and Precision Control of Through Survey of Mine and Roadway

在线阅读下载全文

作  者:陈兴隆 Chen Xinglong(School of Architectural Engineering,Zhengzhou Business University,Henan Zhengzhou 450000)

机构地区:[1]郑州商学院建筑工程学院,河南郑州450000

出  处:《山东煤炭科技》2021年第4期159-161,共3页Shandong Coal Science and Technology

摘  要:为保证伯方煤矿羊圈港进风斜井与二水平西翼轨道大巷顺利贯通,对地面近井点联测、井下控制网联测、巷道导线联测方案进行阐述。分析计算伯方煤矿进风斜井贯通测量误差,经计算贯通测量高程误差闭合差fH为±139 mm,f_(h容)为±0.248 m,f_(H)<f_(h容),满足高程精度限差要求。经后期对贯通误差进行实测,贯通平面纵向误差为+0.063 m,横向误差为-0.14 m,贯通高程误差为+0.11 m,满足巷道使用条件。In order to ensure the smooth connection between Yangquangang air intake inclined shaft and the second level west wing track roadway in Bofang Coal Mine,the joint measurement schemes of ground near well point,underground control network and roadway traverse are described.Through the analysis and calculation of the through survey error of the air intake inclined shaft in Bofang Coal Mine,the closure error f_(H) of the through survey elevation error is±139 mm,f_(h允)is allowed to be±0.248 m,and f_(H)<f_(h允)is allowed to meet the requirements of the elevation accuracy tolerance.According to the actual measurement of the through error in the later stage,the longitudinal error of the through plane is+0.063 m,the transverse error is-0.14 m,and the through elevation error is+0.11 m,which meets the use conditions of the roadway.

关 键 词:贯通测量 平面控制 高程控制 精度控制 

分 类 号:TD175.5[矿业工程—矿山地质测量]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象