大坡度掘进、小半径盾构到达施工技术  

Construction Technology of Large Slope Excavation and Small Radius Shield Arrival

在线阅读下载全文

作  者:刘元龙 LIU Yuanlong(Shanghai Civil Engineering Group Co.,Ltd.of CREC,Shanghai,200000,China)

机构地区:[1]中铁上海工程局集团有限公司,上海200000

出  处:《工程建设(维泽科技)》2021年第4期55-57,共3页Engineering Construction

摘  要:针对34‰大纵坡、300m小半径曲线盾构接收施工技术要点。本文以杭州地铁7号线工程九工区盾构项目为例,着重从重难点把握、施工技术措施等方面,探索大坡度、小半径接收盾构施工技术,以达到为后续施工起借鉴作用的目的。The key points of receiving construction technology for 34‰large longitudinal slope and 300m small radius curve shield machine.Taking the shield project of No.9 work area of Hangzhou Metro Line 7 project as an example,this paper explores the construction technology of large slope and small radius receiving shield from the aspects of key and difficult points and construction technical measures,so as to achieve the purpose of reference for subsequent construction.

关 键 词:大坡度、小半径盾构接收 施工技术 

分 类 号:U455.7[建筑科学—桥梁与隧道工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象