金属矿山地下大型卷扬机硐室施工  被引量:1

Construction of Underground Large Hoist Chamber in Metal Mine

在线阅读下载全文

作  者:任辉 REN Hui(No.31 Engineering Division,China Coal First Construction Company Limited,Handan 056003,China)

机构地区:[1]中煤第一建设有限公司第三十一工程处,河北邯郸056003

出  处:《建井技术》2021年第2期18-21,共4页Mine Construction Technology

摘  要:玲珑矿区深部开采工程主井区-190 m卷扬机硐室断面大,长度较短。为确保硐室快速施工,采用导硐施工加分层正台阶施工方法开挖,采用锚网喷临时支护+钢筋混凝土浇筑联合支护形式,收到预期效果。整个硐室实际施工工期仅为5个月,比计划工期提前了1个月;并且施工安全,实现了安全快速施工。In a main shaft area of the deep mining project in Linglong Mining Area,a-190 m hoist chamber had a large cross section and a short length.In order to ensure the rapid construction of the chamber,the chamber was excavated with a pilot hole construction with a slicing forward step construction method.A combined support with a bolt/steel mesh/shotcreting temporary support and a reinforced concrete pouring was conducted for the chamber.An expected result was obtained.The actual construction period of the whole chamber was only five months and was one month ahead of the scheduled construction period.The construction of the chamber was safe and a safety rapid construction of the chamber was realized.

关 键 词:卷扬机硐室 导硐施工 分层施工 辅助斜坡道 溜矸天井 

分 类 号:TD264.3[矿业工程—矿井建设]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象