某钢铁企业水处理站立式改造工程实例  被引量:1

A project case of water treatment station vertical modification in an iron and steel enterprise

在线阅读下载全文

作  者:金亚飚 JIN Ya-biao(Baowu Water Technology Co.,Ltd.,Shanghai 201900,China)

机构地区:[1]宝武水务科技有限公司,上海201900

出  处:《工业用水与废水》2021年第3期46-49,共4页Industrial Water & Wastewater

摘  要:某钢铁企业水处理站针对无地可用和不允许停产改造的现状,采用了创新性立式改造方案,重点介绍了改造工程的立式设计及施工过程。新增水处理设施采用竖向布置,设备依托框架和平台直接设置于现有水处理站上方,无须新增占地,不影响原有水处理站的正常生产;大量采用一体化设备、模块化设备和预制管道,现场组装,大幅度缩短建设时间。As no land is available and no stopping production is allowed in a water treatment station of an iron and steel enterprise,an innovative vertical modification scheme was adopted,and the vertical design and construction process of the modification project were emphatically introduced.The newly added water treatment facilities were arranged vertically,the equipment was directly arranged above the existing water treatment station on the basis of the steel frame and platform,no additional land was needed and the normal production of the existing water treatment station was not affected.A large number of integrated equipments,modular equipments and pre-fabricated piping were used and field-assembled,the construction time was greatly reduced.

关 键 词:钢铁企业 水处理站改造 立式设计 一体化 模块化 预制管道 

分 类 号:X703.1[环境科学与工程—环境工程] X505

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象