关于混凝土叠合梁浇筑方案的研究  

Research on Pouring Plan of Concrete Composite Beam

在线阅读下载全文

作  者:李旭[1] 王东[1] 孙武卫 彭博 刘运龙 LI Xu;WANG Dong;SUN Wuwei;PENG Bo;LIU Yunlong(Faculty of Civil Engineering and Architecture,Kunming University of Science and Technology,Kunming 650500;不详)

机构地区:[1]昆明理工大学建筑工程学院,昆明650500 [2]云南博晖房地产开发有限公司,昆明650500

出  处:《工业安全与环保》2021年第8期21-24,共4页Industrial Safety and Environmental Protection

摘  要:大体积混凝土梁浇筑施工过程中,难以避免由于体积过大出现的变形,进而造成梁下支撑的脚手架在搭设时,出现安全隐患和经济性差等问题。通过理论计算和有限元软件ANSYS模拟,结合工程实例,对叠合梁采取分两层浇筑的方式,确定合适的先浇高度,以改进搭设梁下支撑间距和缩短支撑拆除时间。During the construction of large-volume concrete beams,it is difficult to avoid the deformation due to the excessive volume,which will cause safety hazards and poor economic efficiency when erecting the scaffold supported under the beam.Through theoretical calculations and finite element software ANSYS simulation,and combined with engineering examples,the composite beam is poured in two layers to determine the appropriate first pouring height,improve the spacing between the supports under the erected beams and to shorten the support removal time.

关 键 词:叠合梁 先浇高度 支撑体系 支撑拆除 

分 类 号:TU7[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象