摘  要:北京地铁17号线望京西站-勇士营站区间暗挖横通道下穿2条高压燃气管,施工中根据现场监测结果,分析在富水敏感地层中暗挖大断面隧道施工对燃气管线的影响,对沉降超标的管线采取隔离措施进行2次保护,确保了大断面隧道顺利穿越燃气管线。Two high-pressure gas pipes passes underneath the underground excavated cross passage between Wangjingxi Station and Yongshiying Station of Beijing Metro Line 17.According to on-site monitoring results,impact of construction of undergound excavated large cross section tunnel in the water-rich sensitive stratum on the gas pipeline is analyzed,isolation measures for secondary protection of pipelines with excessive settlement are taken to ensure the large cross-section tunnel passes through the gas pipeline smoothly.

关 键 词:大断面下穿管线 地表沉降 管线变形 现场监测 

分 类 号:TU74[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象