摘  要:北京地铁17号线盾构接收井横通道开挖施工中,发现下层导洞含水量大,虽采用全断面注浆残余水仍难以控制。对此将小型潜水泵接入轻型井点作为暗挖隧道止水措施,经计算根据隧道的最大涌水量确定了轻型井的各项参数;采用倾斜成孔等施工工艺,取得了良好的止水效果。During excavation of cross passage of shield receiving shaft of Beijing Metro Line 17, it was found that the lower pilot tunnel has a large water content, and the residual water is still difficult to control despite the use of full-section grouting. For the above, a small submersible pump is connected to a light well point as a water-stop measure for the underground excavation tunnel. After calculation, various parameters of the light well are determined according to maximum water inflow of the tunnel;and construction techniques such as inclined hole formation have been used to achieve good water-stopping effect.

关 键 词:轻型井点 隧道工程 止水效果 

分 类 号:TU74[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象