某渠首除险加固枢纽布置方案比选  被引量:1

Comparison and Selection of the Layout Scheme of Hazard Removal and Reinforcement of a Canal Head Hub

在线阅读下载全文

作  者:于志昂 YU Zhiang(Changji Fanghui Hydropower Design Co.,Ltd.Changji 831100,China)

机构地区:[1]新疆昌吉方汇水电设计有限公司,新疆昌吉831100

出  处:《河南水利与南水北调》2021年第5期60-61,共2页Henan Water Resources & South-to-North Water Diversion

摘  要:通过工程布置、引水、冲沙效果、运行管理及投资等方面综合分析比较,文章中方案三(拦河闸坝式)具有布置简单、枢纽工程量较小、引水条件好、河道小流量冲砂效果较好、工程投资少以及后期运行安全、管理方便等优势,故渠首除险加固方案采用拦河闸坝式取水枢纽。Through the comprehensive analysis and comparison of project layout,water diversion,and washing effect,operation management and investment etc,scheme 3( River Barrage type) is obtained. t has the advantages of simple layout,small project amount,good water diversion conditions,good sand washing effect with small river flow,less project investment and safe operation in the later period and convenient management. Therefore,the River Barrage type of water intake hub is adopted in the hazard removal and reinforcement scheme.

关 键 词:渠首选 枢纽布置 方案比选 

分 类 号:S274[农业科学—农业水土工程]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象