超高层项目消火栓系统永临结合优势分析  被引量:3

Analysis on Permanent-temporary Combination Advantages of Fire Supervisor in Super High-rise Project

在线阅读下载全文

作  者:刘洋[1] 王荣来 Liu Yang;Wang Rong-lai

机构地区:[1]中国建筑第二工程局有限公司华南分公司,广东深圳518000

出  处:《建筑技术开发》2021年第17期21-22,共2页Building Technology Development

摘  要:临时消防和施工用水永临结合是通过提前插入局部消火栓系统管线,使之成为机电安装工程中永久消防功能的一部分。利用永临结合的方式可有效节约成本、缩短工期,避免漏水隐患,防止对后期精装工序的影响,杜绝了消防用水的真空期,同时,满足“绿色建筑、节能环保”的国家政策。该永临结合方式的具体优点以某项目超高层建筑为例进行说明。Temporary fire fighting and construction water combination is formed by inserting local fire hydrant system pipeline,to be a part of permanent fire protection function in mechanical and electrical installation works.The use of permanent and temporary combination can effectively save cost and shorten construction period,avoid water leakage hidden trouble,prevent impact on later fine decoration process,and put an end to the vacuum period of fire water.At the same time,the national policy of"green building,energy conservation and environmental protection"is met,and specific advantages are illustrated with a project of super high-rise building as an example.

关 键 词:临时消防 施工用水 永临结合 

分 类 号:TU74[建筑科学—建筑技术科学]

 

参考文献:

正在载入数据...

 

二级参考文献:

正在载入数据...

 

耦合文献:

正在载入数据...

 

引证文献:

正在载入数据...

 

二级引证文献:

正在载入数据...

 

同被引文献:

正在载入数据...

 

相关期刊文献:

正在载入数据...

相关的主题
相关的作者对象
相关的机构对象