作 者:范志远 FAN Zhiyuan(China Railway 12^(th) Bureau Group 4^(th) Engineering Co.Ltd.,Xi’an Shaanxi 710054,China)
机构地区:[1]中铁十二局集团第四工程有限公司,陕西西安710054
出 处:《铁道建筑技术》2021年第10期40-44,共5页Railway Construction Technology
基 金:中国铁路总公司科技研究开发计划(2017G007-G)。
摘 要:以银西铁路某隧道为依托,利用现场测试、数值模拟方法对大断面土质隧道围岩压力、二次衬砌内力、拱架应力、混凝土内力展开研究。结果表明:大断面土质隧道围岩压力大致分为急剧增长、减速增长、趋于平缓三个阶段,在空间分布上,表现为左侧>右侧、拱顶>仰拱的变化规律;围岩接触压力在空间范围内表现为拱顶、拱底较大。初支混凝土变化曲线基本呈受压状态,拱顶处围岩压力值较大;随着初期支护闭合成环,围岩应力与位移均表现出随时间增加而减少的趋势,建议施工过程应及时将衬砌结构封闭成环以改善结构整体应力及位移状态。Based on a tunnel of Yinchuan-Xi’an High-speed Railway,the research methods of field test and numerical simulation are used to study the surrounding rock pressure,secondary lining internal force,arch stress and concrete internal force of large section soil tunnel.It is concluded that the surrounding rock pressure of large section soil tunnel can be roughly divided into three stages:rapid growth,deceleration growth and flattening.In terms of spatial distribution,it shows the change law of left side>right side,arch crown>inverted arch;the contact pressure of surrounding rock shows that the arch crown and arch bottom are large in space.The variation curve of the initially supported concrete basically presents the state of compression,and the pressure value of the surrounding rock at the arch crown is large;with the initial support closed into a ring,the stress and displacement of surrounding rock show a decreasing trend with the increase of time.Therefore,it is suggested to close the lining structure into a ring as soon as possible in the construction process to improve the overall stress and displacement state of the structure.
关 键 词:大断面土质隧道 围岩压力 复合衬砌 时空效应 数值分析 现场监测
分 类 号:U456.3[建筑科学—桥梁与隧道工程] U451.2[交通运输工程—道路与铁道工程]
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在载入数据...
正在链接到云南高校图书馆文献保障联盟下载...
云南高校图书馆联盟文献共享服务平台 版权所有©
您的IP:216.73.216.15